| |
St. Louis District Facebook Twitter Flickr Blog YouTube RSS

I-64 Daniel Boone Bridge over the Missouri River

Project Alerts & Updates:

Lane Shifts on Interstate 64 (updated September 2014)

Traffic on eastbound and westbound Interstate 64 are currently shifted to allow crews to make the connection from the current eastbound I-64 to the new Boone Bridge. 

Traffic on eastbound I-64 is shifted to the left both before and after the Boone Bridge.  The lanes have been narrowed to 11-feet and the speed limit in the lane shift has been reduced to 50 mph.  There is no no lane shift on the bridge itself.  The eastbound lane shifts will remain in place until the new eastbound Boone Bridge opens. 

Traffic on westbound I-64 past the Boone Bridge is shifted to the right and the lanes are narrowed to 11-feet.  This lane shift will be in place until the summer of 2015.

 

Schedule Update (updated September 2014)

Construction on the new eastbound Boone Bridge is moving right along, but due to some problems getting foundation work completed in the river last spring we have pushed back the scheduled opening date of the new bridge to late spring of 2015.  However, we are still on track to finish rehabbing the 1980’s bridge next year and will have it open to westbound traffic in late 2015.

The majority of the lane closures for this project that significantly delay traffic are complete since all the concrete is poured for the foundations in the river.  Although there will still be some ramp and lane closures as we proceed with the project, most will take place during non-peak travel times and have little impact to traffic flow.  The lane shifts on eastbound and westbound I-64 will remain in place for several more months. 

Monarch Levee Trail Closed (updated October 2014)

The Monarch Levee Trail remains closed due to construction of the new Boone Bridge.  The trail is closed approximately 1,000 feet on either side of the bridge until construction of the new bridge is complete.  At that time, the trail will be reopened and users will be able to access the Katy Trail in St. Charles County by the pedestrian pathway on the bridge.

             

________________________________________________________________________________________

 

Rendering of the new I-64 Missouri River Bridge

Rendering of new I-64 Daniel Boone Missouri River Bridge and shared-use path

A project to construct a new Daniel Boone Bridge over the Missouri River between St. Louis and St. Charles counties has been funded.  A total of $125 million has been allocated for the project -- that includes money for utility relocation, property acquisition, design and construction of the project.

What is the construction schedule and impact to traffic? (updated September 2014)

2013 = construction begins with work on the new eastbound bridge, the Spirit of St. Louis Blvd bridge over I-64 raised and construction on a new Chesterfield Airport Road Bridge and North Outer Road connection

2014 = the new Chesterfield Airport Road bridge and interchange complete by November 2014

Late Spring 2015 = traffic on the new eastbound bridge by spring 2015

2015 = all traffic in final position in late 2015

2016 = the 1935 westbound bridge will be removed

Why does a new bridge need to be constructed?

The current westbound Daniel Boone Bridge was built in the mid-1930s, making it nearly 80 years old.  It was not designed for interstate level traffic and has reached a point where it needs regular preventative maintenance.  Moreover the current westbound bridge has three narrow lanes that often get congested during peak travel times.

Where will the new bridge be constructed?

The new bridge will be built upstream from the existing two bridges.  Once it is complete, eastbound I-64 traffic will use the new bridge and westbound traffic will be shifted to what is currently the eastbound bridge. 

Will the bridge include a bike-pedestrian lane?

A shared used bicycle/pedestrian trail will be built on the upstream side of the new bridge.  It will include connections off the bridge to the Monarch Levee Trail on the St. Louis County side and to the KATY Trail on the St. Charles County side.

What will happen to the current 1935 westbound bridge? (updated September 2014)

The current westbound bridge will be removed in 2016 by the contractor.

_______________________________________________________________________________________

Walsh-Alberici Team Selected to Build New Bridge

The Missouri Highways and Transportation Commission selected the design-build contractor for the new I-64 Daniel Boone Bridge on July 10, 2012.  The Walsh-Alberici joint venture team, with designer Burns & McDonnell, will build a new bridge to replace the 80-year old westbound bridge. The project will also include removal of the 1935 existing westbound bridge and building a new Chesterfield Airport Road interchange including connecting the North Outer Road to the westbound I-64 on ramp.  The project will build a continuous westbound fourth lane from the Chesterfield Airport Road entrance ramp westbound to the Route 94 exit ramp.  It will also add a shared use path on the new eastbound bridge connecting the KATY trail to the Monarch Levee Trail.

I-64 Daniel Boone Design-Build Procurement Information

The following exhibits from the contractor team show the $111 million Design-Build plans:

Cross section typical on the bridge (pdf)

Elevation view in the river (pdf)

Overall project scope (pdf)

Rendering of new bridge looking east toward St Louis (pdf)

Rendering of new bridge looking west toward St Charles (pdf)

Scenic bike/pedestrian trail bridge overlook (pdf)

Use of all three bridges during construction phases (pdf)

Document Library

________________________________________________________________________________________

Construction Progress Photos (updated October 2014)

 

BooneBoonePic

 

Girders

 

To see more project construction photos on FLICKR, click here.

BooneAerial

Click here to see more aerial photos of the Boone Bridge construction taken in October 2014. here.

To view MoDOT's live construction camera on the St. Charles County end of the bridge, click here.  The camera takes a photograph every 20 minutes or so. 

________________________________________________________________________________________

Sign up for e-updates

MoDOT wants to ensure all stakeholders stay updated about the project. We will send out periodic "e-updates" via e-mail when new information is available. If you would like to be added to this list, please send an e-mail to Boone.Bridge@modot.mo.gov. If you do not have access to e-mail, you can call MoDOT toll-free at 1-888-ASK MODOT (275-6636) for updates on the project.

For more information

Contact Project Director Jim Gremaud at 888-ASK-MODOT (275-6636) or by e-mail at Boone.Bridge@modot.mo.gov.

 
District Map
St. Louis District
spacer
Traveler Information
Traveler Map
Gateway Guide
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Your Local Area Engineer
Report A Road Concern
Mississippi River Bridge
I-270 North
Route 364
I-64 Daniel Boone Bridge
On the Move
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Facebook Twitter Flickr Blog YouTube Franklin Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android