Adair County
Construction Projects:
US 63 - Drainage and sidewalk improvements in Kirksville
Work Zone Info: Inactive
Project Status: 0% complete-
Work zone start date to be scheduled
Estimated Completion: Fall 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Route AA – May 29 pavement repairs; traffic may be reduced to one lane at various locations from US 63 just north of Sublette to end of State Maintenance
Route DD – May 29-30 pavement repairs; traffic may be reduced to one lane at various locations from Route K south of Novinger to end of State Maintenance
Route B – May 30-31 pavement repairs; traffic may be reduced to one lane at various locations from MO 6 north of Kirksville to Route K west of Greentop in Schuyler Co.
Route O – May 31 pavement repairs; traffic may be reduced to one lane at various locations from MO 6 at Novinger to Route D north of Greencastle.
Route 149 – May 31 – June 1 pavement repairs; traffic may be reduced to one lane at various locations from MO 6 at Novinger to MO 156 in Macon Co.
Route D – June 1 pavement repairs; traffic may be reduced to one lane at various locations from MO 149 north of Connelsville to MO 6 at Green Castle in Sullivan Co.
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Routes – May 29 – June 8 striping; moving operation with one lane traffic with blocker truck protecting work zone, watch for wet paint.
Audrain County
Construction Projects:
Route JJ - Resurface from US 54 at Mexico to the end of state maintenance .
Work Zone Info: Inactive
Project Status: 0% complete-Resurfacing to begin in June.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
Route B - Resurface from US 54 through Rush Hill to Route J.
Work Zone Info: Inactive
Project Status: 0% complete-Resurfacing to begin in June.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
Route KK - Resurface from MO 19 at Laddonia to Route B north of Rush Hill.
Work Zone Info: Inactive
Project Status: 0% complete-Resurfacing to begin in June.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
MO 19 - Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles.
Work Zone Info: Inactive
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Maintenance
US 54 Outer Roads – May 29-June 8 grading on gravel outers roads; moving operation with short duration one lane traffic.
Various Minor Routes - May 29-June 8 culvert replacements and ditch work; one lane traffic with flaggers at the work zone.
Various Routes – May 29 – June 8 pothole patching; short duration one lane traffic with blocker truck protecting work zone.
Various Routes - May 29-June 8 sign repairs along shoulders; one lane traffic with blocker truck protecting work zone.
Clark County
Construction Projects
MO 81 - Safe and Sound Bridge replacement at Fox River north of Kahoka
OPEN TO TRAFFIC - May 24, 2012
Macon Project Office-Resident Engineer Jeff Gander
Route D - Safe and Sound Bridge replacement at Little Wyaconda River east of Fairmont
OPEN TO TRAFFIC - May 25, 2012
Macon Project Office-Resident Engineer Jeff Gander
Route D - Safe and Sound Bridge replacement at Wyaconda River south of Kahoka - Bridge to close May 29, 2012 for 58 days
Work Zone Info: Inactive - Road to be closed May 29 with detour over Routes 81, M and Lewis Route E
Project Status: 0% complete- Bridge to close for demolition May 29, weather permitting.
Estimated Completion: July 27, 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Route HH – May 29-30 traffic reduced to one lane for pavement repairs from 7 a.m. to 4 p.m. at various locations from Route Y south to the end of State Maintenance.
Route DD – May 30 road closed from 8 a.m. to 2 p.m. north of Kahoka for culvert replacement approximately 3 miles from Route C junction; alternate routes must be used during this time.
Route BB – May 31 traffic reduced to one lane for pavement repairs from 7 a.m. to 4 p.m. at various locations from Route H to the end of State Maintenance at Davis.
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Minor Routes - May 29-June 8 spraying herbicide for weed control along shoulders; one lane traffic with blocker truck protecting work zone.
Knox County
Construction
Route M - Safe and Sound Bridge replacement at Middle Fabius River south of Rutledge near the Community of Millport - Bridge to close for 58 days
Work Zone Info: Inactive - Road to be closed June 11 with detour over Routes V and K
Project Status: 0% complete- Demolition begins June 11, weather permitting.
Estimated Completion: August 8, 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Minor Routes - May 29-June 8 spraying herbicide for weed control along shoulders; one lane traffic with blocker truck protecting work zone.
Lewis County
Construction
MO 16 - Safe and Sound Bridge replacement at Sugar Creek east of Monticello - Bridge to close June 4, 2012 for 49 days
Work Zone Info: Inactive - Road to be closed June 4 with detour over Routes F, E and A
Project Status: 0% complete- Bridge to close for demolition June 4, weather permitting.
Estimated Completion: July 23, 2012
Macon Project Office-Resident Engineer Jeff Gander Maintenance
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Minor Routes - May 29-June 8 spraying herbicide for weed control along shoulders; one lane traffic with blocker truck protecting work zone.
Lincoln County
Construction Projects
MO 79 - Bridge project at Sandy Creek 1 mile north of Route Y at Foley
Work Zone Info: Road to close July 15
Detour Local and Tourist Traffic on Routes Y, W and B
Detour Option Commercial Traffic on MO 47, US 61 and Route B
Project Status: 0% complete-
Road to be closed from July 15-Oct. 1
Estimated Completion: October 2012
Troy Project Office-Resident Engineer Rick Domzalski
MO 47 - Resurface driving lanes and shoulders from west of Route J to Main St. in Troy
Work Zone Info:
All lanes open to traffic for Memorial Day weekend beginning Thurs., May 24, work resumes on Tues., May 29. Nighwork 8 p.m. to 5 a.m. with one lane traffic and flaggers
Project Status: 10% complete- Resurfacing in progress.
Estimated Completion: end of June 22,2012
Troy Project Office-Resident Engineer Rick Domzalski
US 61 - Pavement repair and resurfacing north and southbound lanes from just north of Route OO in Pike Co. to Route B in Lincoln Co., 13.2 miles
Work Zone Info: Inactive - One lane traffic beginning June 5-July 3.
Project Status: 0% complete- Milling operations June 5-12; paving operations scheduled for June 13-20.
Estimated Completion: July 3, 2012
Troy Project Office-Resident Engineer Rick Domzalski
US 61 - Resurface northbound lanes and shoulders from just north of Route Z to just south of Route K, 9.5 miles
Work Zone Info: Inactive - One lane traffic beginning June 22-July 31.
Project Status: 0% complete- Milling operations June 22-July 12; paving operations for July 13-July 31.
Estimated Completion: August 9
Troy Project Office-Resident Engineer Rick Domzalski
Route A - Seal coat from Route DD to Interstate 70 in Warren Co., 12.9 miles
Work Zone Info: Inactive - One lane traffic June 27-29.
Project Status: 0% complete-Seal coat begins June 27-29.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route JJ - Seal coat from Route W south junction to MO 79, 8 miles
Work Zone Info: Inactive - One lane traffic June 14-15.
Project Status: 0% complete-Seal coat begins June 14-15.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route B - Seal coat from US 61 to MO 79, 10.2 miles
Work Zone Info: Inactive - One lane traffic June 16-20.
Project Status: 0% complete-Seal coat begins June 16-20.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route OO - Seal coat from Route C to end of state maintenance near Chain of Rocks, 1.8 miles
Work Zone Info: Inactive - One lane traffic July 2.
Project Status: 0% complete-Seal coat begins July 2.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Route U – May 29 traffic reduced to one lane for pavement repairs from 6 a.m. to 4:30 p.m. at various locations from US 61 south of Moscow Mills to MO 47 south of Hawk Point.
MO 47 - May 29-31 traffic reduced to one lane for pavement repairs from 6 a.m. to 4:30 p.m. at various locations from just west of US 61 at Troy west to Hawk Point.
Route D - June 4 traffic reduced to one lane for pavement repairs from 6 a.m. to 4:30 p.m. at various locations from Route O at Olney to Route E.
Route TT - June 5 traffic reduced to one lane for pavement repairs from 6 a.m. to 4:30 p.m. at various locations from Route D and O north to the end of State Maintenance.
Route O - June 6 traffic reduced to one lane for pavement repairs from 6 a.m. to 4:30 p.m. at various locations from MO 161 south of New Hartford to Route E at Olney.
Route E - June 7 traffic reduced to one lane for pavement repairs from 6 a.m. to 4:30 p.m. at various locations from US 61 to Route O at Olney.
Various Minor Routes - May 29 -June 7 mowing; traffic reduced to one lane with blocker truck at the work zone.
Macon County
Maintenance
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Routes – May 29 – June 8 striping; moving operation with one lane traffic with blocker truck protecting work zone, watch for wet paint.
Various Routes - May 29-June 7 sign repairs and drainage work along shoulders; one lane traffic with blocker truck protecting work zone.
Marion County
Construction
MO 168 – Bridge replacement over North River 1.4 miles west of Route C near Palmyra.
Work Zone Info: ROAD CLOSED. Detour over Routes C, Z and 168
Project Status: 5% complete - Demolition of old bridge continues and will work on coring drilled shafts.
Estimated Completion: fall 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
US 24/61 Palmyra – Intersection improvements at Palmyra from Main Cross St. to Thompson St.
Work Zone Info: Inactive. One lane traffic through work zone area.
Project Status: 0% complete - Inactive. Project has not been scheduled.
Estimated Completion: October 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Maintenance
US 61 – May 29 – June 8 pothole patching; short duration one lane traffic with blocker truck protecting work zone.
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Routes - May 29-June 8 sign repairs along shoulders; one lane traffic with blocker truck protecting work zone.
Various Routes – May 29 – June 8 intersection marking and striping; moving operation with one lane traffic with blocker truck protecting work zone, watch for wet paint.
Monroe County
Construction Projects
Routes 107 and FF - Preventative maintenance on Mark Twain Lake bridges over North Fork and South Fork Salt River on Route 107, and North Fork Salt River Bridge on Route FF; substructure repairs and modifications, expansion joint replacement, removal and replacement of asphalt surface and upgrading the existing guardrail. Contractor- PCI Roads, LLC.
Project Status: COMPLETED - OPEN TO TRAFFIC
Macon Project Office-Resident Engineer Jeff Gander
Route CC - Safe and Sound Bridge replacement at Clear Creek south of Shelbina
Project Status: COMPLETED - OPEN TO TRAFFIC
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
US 24 - Resurface driving lanes from Randolph County line to just east of Route 15 near Paris
Work Zone Info: All lanes open to traffic for Memorial Day weekend beginning Thurs., May 24, work resumes on Tues., May 29.
Project Status: 11% complete-Resurfacing and coldmilling through Madison beginning Tues., May 29.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance:
Various Minor Routes - May 29-June 8 culvert replacements; one lane traffic with flaggers at the work zone.
Various Routes – May 29 – June 8 pothole patching; short duration one lane traffic with blocker truck protecting work zone.
Various Routes - May 29-June 8 sign repairs along shoulders; one lane traffic with blocker truck protecting work zone.
Montgomery County
Construction Projects:
MO 161 - Safe and Sound Bridge replacement at Elkhorn Creek east of Montgomery City
Work Zone Info: ROAD CLOSED with detour over MO 19 and Route CC.
Project Status: 5% complete- Pre-boring and bent work, weather permitting.
Estimated Completion: July 9, 2012
Troy Project Office-Resident Engineer Rick Domzalski
MO 94 – Seal coat from MO 19 to Route T at Augusta near the Warren/St. Charles Co. line, 32.670 miles.
Work Zone Info: Inactive -One lane traffic; work scheduled to begin July 16-23
Project Status: 0% complete-Seal coat
work scheduled to begin July 16-23.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route K – Seal coat from Route D in Callaway County to the Montgomery County line, 5.885 miles.
Work Zone Info: Inactive - One lane traffic
Project Status: 0% complete-Seal coat to be scheduled at a later date.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route D – Seal coat from I-70 at Williamsburg in Callaway County to MO 94 east of Portland near the Montgomery County line, 18.336 miles.
Work Zone Info: Inactive - One lane traffic
Project Status: 0% complete-Seal coat to be scheduled at a later date.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Various Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Pike County
Construction Projects:
Route D - Safe and Sound Bridge replacement at Little Calumet Creek just south of Route N near Calumet - Bridge to close May 7, 2012 for 58 days
Work Zone Info: ROAD CLOSED with detour over MO 79 and Routes N, W and WW.
Project Status: 20% complete- Working on end bents and pour caps at intermediate bents, weather permitting.
Estimated Completion: June 30, 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
US 54 - Safe and Sound Bridge replacement at Noix Creek between Bowling Green and Louisiana- Bridge to close June 18, 2012 for 50 days
Work Zone Info: Inactive - June 18 road to be closed
Commercial Vehicle Detour - Recommended Detour Routes over US 54, MO 79 south, Route B west, US 61 North or South
Local and Tourism Detour - Recommended Detour Routes over US 54, Route UU, US 61 North or South
Project Status: 0% complete- Road to be closed at bridge June 18 for demolition to begin, weather permitting.
Estimated Completion: August 7, 2012
Troy Project Office-Resident Engineer Rick Domzalski
US 54 - Safe and Sound Bridge replacement at North Fork of Noix Creek between Bowling Green and Louisiana- Bridge to close June 25, 2012 for 40 days
Work Zone Info: Inactive - June 25 road to be closed
Commercial Vehicle Detour - Recommended Detour Routes over US 54, MO 79 south, Route B west, US 61 North or South
Local and Tourism Detour - Recommended Detour Routes over US 54, Route UU, US 61 North or South
Project Status: 0% complete- Road to be closed at bridge June 25 for demolition to begin, weather permitting.
Estimated Completion: August 4, 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route UU - Resurface from US 61 near Bowling Green to US 54 near Louisiana
Project Status: COMPLETED - ALL LANES OPEN TO TRAFFIC
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
MO 79 - Seal coat from Ralls County line to Route TT near Ashburn.
Work Zone Info: Inactive - Work tentatively scheduled to begin after May 1.
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Route Z - Seal coat from
Route 161 to US 61 in Pike and Lincoln Counties, 16.9 miles
Work Zone Info: Inactive - One lane traffic June 6-13.
Project Status: 0% complete-Seal coat begins June 6-13.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route H - Seal coat
from Route W south junction to MO 79, 3.9 miles
Work Zone Info: One lane traffic June 5.
Project Status: 0% complete-Seal coat begins June 5.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
US 61 - Pavement repair and resurfacing north and southbound lanes from just north of Route OO in Pike Co. to Route B in Lincoln Co., 13.2 miles
Work Zone Info: Inactive - One lane traffic beginning June 12.
Project Status: 0% complete- Milling and paving operations scheduled to begin June 12.
Estimated Completion: July 3
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Route O – June 6 traffic reduced to one lane for pavement repairs from 6:30 a.m. to 5 p.m. at various locations from MO 161 south of New Hartford to Route E at Olney in Lincoln County.
Various Routes – May 29 – June 8 pothole patching; short duration one lane traffic with blocker truck protecting work zone.
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Routes - May 29-June 8 spraying herbicide for weed control along shoulders; one lane traffic with blocker truck protecting work zone.
Ralls County
Construction Projects:
MO 19 - Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles.
Work Zone Info: Inactive - Job has not been scheduled
Project Status: 0% complete- A preconstruction conference will be scheduled to determine the start date.
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Route T - Resurface from just south of MO 79 to Route N south of Hannibal .
Work Zone Info: Inactive - Work tentatively scheduled to begin June 1.
Project Status: 0% complete- Inactive
Estimated Completion: Fall 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
MO 154 - Resurface from MO 19 to US 54 near Hutchison between Curryville and Vandalia.
Work Zone Info: Inactive
Project Status: 0% complete-Resurfacing to begin in June.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
Route E - Seal coat from MO 79 to end of State maintenance near Saverton.
Work Zone Info: Inactive - Work tentatively scheduled to begin after May 1.
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Route T - Seal coat from Route N south of Hannibal to MO 79 near Ashburn .
Work Zone Info: Inactive - Work tentatively scheduled to begin June 1.
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Route V - Seal coat from Ralls Street in New London to Route T.
Work Zone Info: Inactive - Work tentatively scheduled to begin after May 1.
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Route N - Seal coat from Route T to MO 79 near Saverton.
Work Zone Info: Inactive -Work tentatively scheduled to begin after May 1.
Project Status: 0% complete- Inactive
Estimated Completion: Summer 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
Maintenance
Various Routes – May 29 – June 8 pothole patching; short duration one lane traffic with blocker truck protecting work zone.
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Randolph County
Construction Projects
Route B - Resurfacing from Route A to US 63 near Clark, 8.541 miles
Work Zone Info: All lanes open to traffic for Memorial Day weekend beginning Thurs., May 24, work resumes on Tues., May 29.
Project Status: 65% complete-Resurfacing resumes with one lane traffic at work zone on Tues., May 29.
Estimated Completion: Summer 2012
Macon Project Office-Resident Engineer Jeff Gander
Route M - Resurfacing from US 63 in Moberly to MO 151 at the Monroe county line, 10.869 miles
Project Status: COMPLETED-ALL LANES OPEN TO TRAFFIC
Macon Project Office-Resident Engineer Jeff Gander
MO 3 - Resurfacing from Route T to north of US 24 near Clifton Hill, 12.721 miles
Project Status: COMPLETED-ALL LANES OPEN TO TRAFFIC
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Route NN – May 29-31 extensive pavement repairs; traffic reduced to one lane at various locations from the Monroe County line to Hwy 63, 6:30 a.m. to 4:30 p.m.
Route O – June 4-5 extensive pavement repairs; traffic reduced to one lane at various locations to Hwy C, 6:30 a.m. to 4:30 p.m.
Route Z – June 6-7 extensive pavement repairs; traffic reduced to one lane at various locations from Hwy C, 6:30 a.m. to 4:30 p.m.
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Schuyler County
Maintenance
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Minor Routes - May 29-June 8 spraying herbicide for weed control along shoulders; one lane traffic with blocker truck protecting work zone.
Scotland County
Maintenance
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Minor Routes - May 29-June 8 spraying herbicide for weed control along shoulders; one lane traffic with blocker truck protecting work zone.
Shelby County
See Route 36 Four-Lane Webpage
Construction Projects:
Route H - Safe and Sound Bridge replacement at Hilton Branch south of Leonard - Bridge to close May 7, 2012 for 39 days
Work Zone Info: ROAD CLOSED with detour over MO 151 and Route K .
Project Status: 90% complete- Contractor plans to poly card, work on asphalt approaches and guardrail installation, weather permitting.
Estimated Completion: June 1, 2012
Macon Project Office-Resident Engineer Jeff Gander
MO 151 - Safe and Sound Bridge replacement at Otter Creek south of Clarence - Bridge to close May 31, 2012 for 45 days
Work Zone Info: Inactive - Road to be closed May 31 with detour over US 36, and Routes TT and DD .
Project Status: 0% complete- Road to be closed at bridge May 31 for demolition to begin, weather permitting.
Estimated Completion: July 15, 2012
Hannibal Project Office-Resident Engineer Martin "Marty" Lincoln
MO 15 – Install guardrail near Elm Street at US 36 interchange at Shelbina
Work Zone Info: Inactive. One lane traffic through work zone area.
Project Status: 0% complete - Inactive. Project has not been scheduled.
Etimated Completion: October 2012
Macon Project Office-Resident Engineer Jeff Gander
Maintenance
Route W – May 29 extensive pavement repairs at various locations from
MO 168 to the end of State Maintenance at Lewis County line; traffic reduced to one lane, 6:30 a.m. to 4:00 p.m.
Route T – May 30 extensive pavement repairs at various locations from
US 36 at Lakenan north to MO 168 west of Emden; traffic reduced to one lane, 6:30 a.m. to 4:00 p.m.
Route AA – May 31 and June 4 extensive pavement repairs at various locations from
MO 15 south of Shelbyville to Route T; traffic reduced to one lane, 6:30 a.m. to 4:00 p.m.
Route M – June 5 extensive pavement repairs at various locations from
MO 15 near Bethel west mo MO 151 at Leonard; traffic reduced to one lane, 6:30 a.m. to 4:00 p.m.
Route BB – June 5 extensive pavement repairs at various locations; traffic reduced to one lane, 6:30 a.m. to 4:00 p.m.
Route K – June 6 extensive pavement repairs at various locations from
MO 15 at Shelbyville west to MO 151; traffic reduced to one lane, 6:30 a.m. to 4:00 p.m.
Route N – June 7 extensive pavement repairs at various locations from
US 36 at Lentner north to Route K; traffic reduced to one lane, 6:30 a.m. to 4:00 p.m.
Various Minor Routes - May 29-June 8 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Routes – May 29 – June 8 pothole patching; short duration one lane traffic with blocker truck protecting work zone.
Various Routes - May 29-June 8 sign repairs along shoulders; one lane traffic with blocker truck protecting work zone.
Warren County
Construction Projects:
Route A - Safe and Sound Bridge replacement at Camp Creek east of Truxton
Work Zone Info: ROAD CLOSED detour over MO 47 and Routes W and A.
Project Status: 95% complete-Contractor plans to open bridge Tuesday, May 29 in conditions permit.
Estimated Completion: May 29, 2012
Troy Project Office-Resident Engineer Rick Domzalski
I-70 eastbound – Resurface driving lanes and shoulders from the St. Charles Co. line to Wright City
Work Zone Info:
All lanes open to traffic for Memorial Day weekend beginning Thurs., May 24, work resumes on Tues., May 29. Night work with one lane traffic weekly from 7 p.m. to 5 a.m. Sunday evening/Friday morning.
Project Status: 0% complete- Resurfacing in progress.
Estimated Completion: July 2012
Troy Project Office-Resident Engineer Rick Domzalski
MO 94 – Seal coat from MO 19 to Route T at Augusta near the Warren/St. Charles Co. line, 32.670 miles.
Work Zone Info: Inactive - One lane traffic;
work scheduled to begin July 16-23
Project Status: 0% complete-Seal coat
work scheduled to begin July 16-23.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route MM - Resurface from Old 40 to Route M at Warrenton
Work Zone Info: Inactive
Project Status: 0% complete- Milling and resurfacing operations to be scheduled at a later date.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route AA - Resurface from Route 47 to the end of state maintenance
Work Zone Info: Inactive
Project Status: 0% complete- Milling and resurfacing operations to be scheduled at a later date.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route H - Seal coat from just south of I-70 to Route M, 3.6 miles
Work Zone Info: Inactive - One lane traffic June 21.
Project Status: 0% complete-Seal coat begins June 21.
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Route W- Seal coat from Warrenton north to Route A, 10.2 miles
Work Zone Info: Inactive -One lane traffic June 22-26
Project Status: 0% complete-Seal coat begins June 22-26
Estimated Completion: Summer 2012
Troy Project Office-Resident Engineer Rick Domzalski
Maintenance
Route CC – May 29 traffic reduced to one lane for pavement repairs from 6 a.m. to 4 p.m. at various locations from MO 47 south of Warrenton to the end of State Maintenance.
MO 47 – May 29-30 traffic reduced to one lane for pavement repairs from 6 a.m. to 4 p.m. at various locations from Warrenton to Hawk Point.
Route F – May 30 traffic reduced to one lane for pavement repairs from 6 a.m. to 4 p.m. at various locations from Wright City to the end of State Maintenance near Innsbrook.
Route M – June 4-5 traffic reduced to one lane for pavement repairs from 6 a.m. to 4 p.m. at various locations from MO 47 near Truesdale to Route T.
Route U – June 6-7 traffic reduced to one lane for pavement repairs from 6 a.m. to 4 p.m. at various locations from MO 47 at Warrenton to MO 94.
Various Minor Routes - May 29-June 7 mowing along shoulders on all minor routes; one lane traffic with blocker truck protecting work zone.
Various Routes - May 29-June 7 sign repairs along shoulders; one lane traffic with blocker truck protecting work zone.
|